Prepared 2026-10-11 (America/Chicago). Labels: FACT = stated by Ørsted in its Annual Report 2025 (approved 6 Feb 2026), its 6 Feb 2026 company announcement, its Interim Report for H1 2026 (13 Aug 2026) or the matching company announcement; SECONDARY = third-party reporting (none used for numbers below); INFERENCE = arithmetic or reasoning by this project from company-stated numbers. No invented figures. Fiscal year = calendar year; Ørsted reports in DKK. Euro equivalents on the canvas (revenue ≈ €9.8B, net profit ≈ €0.42B) are INFERENCE at the krone peg of about DKK 7.46/EUR; Ørsted itself gives only one euro figure (EBITDA ex one-offs DKK 25.1B ≈ EUR 3.4B). Interim figures are unaudited.
Develop and build offshore wind, sell the power on long-term government-backed contracts, and sell stakes in the big farms to partners who also pay Ørsted to build them — which funds the next build. FY2025 revenue was DKK 73.2B (+3%) but EBITDA was DKK 22.4B (DKK 25.1B excluding new partnerships and cancellation fees) and net profit only DKK 3.2B, with free cash flow of −DKK 18.9B because gross investments (DKK 55.0B) were more than twice operating cash flow (DKK 23.7B). A DKK 60B rights issue and ~DKK 46B of divestment proceeds cut net debt to DKK 19.0B.
FY2025 (Annual Report, FACT unless noted)
H1 2026 (Interim report, FACT, unaudited)
Key Partners: Apollo, Cathay, Brookfield, Danish State, Equinor, Siemens Gamesa and other suppliers, governments and grid operators. Key Activities: develop, build, operate, farm-down, trade and optimise, OSONIC. Key Resources: capacity, leases and grid connections, people, balance sheet, know-how. Value propositions: price-certain clean power, delivery of offshore wind, contracted-cash-flow stakes. Customer relationships: long contracts, availability, partner co-ownership, regulators, communities. Channels: auctions and tenders, contracts and PPAs, power exchanges, partner negotiations, B2B. Customer segments: governments and subsidy schemes, wholesale markets, heat customers, co-investors. Cost structure: cost of sales, people, D&A, financing, impairments, capex. Revenue streams: generation, grants, construction agreements, resold power, heat, gas, services; farm-down proceeds as funding.
# Ørsted A/S (Nasdaq Copenhagen: ORSTED) — research brief (BMC #064 on gallery, queue id 63)
Prepared 2026-10-11 (America/Chicago). Labels: **FACT** = stated by Ørsted in its Annual Report 2025 (approved 6 Feb 2026), its 6 Feb 2026 company announcement, its Interim Report for H1 2026 (13 Aug 2026) or the matching company announcement; **SECONDARY** = third-party reporting (none used for numbers below); **INFERENCE** = arithmetic or reasoning by this project from company-stated numbers. No invented figures. Fiscal year = calendar year; Ørsted reports in **DKK**. Euro equivalents on the canvas (revenue ≈ €9.8B, net profit ≈ €0.42B) are INFERENCE at the krone peg of about DKK 7.46/EUR; Ørsted itself gives only one euro figure (EBITDA ex one-offs DKK 25.1B ≈ EUR 3.4B). Interim figures are unaudited.
## Sources (accessed 2026-10-11)
- Annual Report 2025 (PDF): https://cdn.orsted.com/-/media/annual-2025/annual-report-2025.pdf (also https://orsted.com/annualreport2025)
- Company announcement 6 Feb 2026 (full-year 2025 results): https://via.ritzau.dk/announcement/14785310?lang=en&publisherId=13560592
- Interim financial report H1 2026 (PDF): https://via.ritzau.dk/ir-files/13560592/15087992/25458/Interim%20financial%20report%20H1%202026.pdf
- Company announcement 13 Aug 2026 (H1 2026): https://orsted.com/en/company-announcement-list/2026/08/orsted-continues-its-strategic-progress-delivers-s-150879921
- Company: https://orsted.com
- Logo: no official mark obtained; the logo is a project monogram ("Ø" on a blue tile), **not** Ørsted's official mark. Trademark of Ørsted A/S; identification only.
- Raw text in /workspace/orsted-src/ (ar25.txt, h1.txt, ca.txt).
## Teaching arc
**Develop and build offshore wind, sell the power on long-term government-backed contracts, and sell stakes in the big farms to partners who also pay Ørsted to build them — which funds the next build.**
FY2025 revenue was **DKK 73.2B (+3%)** but EBITDA was DKK 22.4B (DKK 25.1B excluding new partnerships and cancellation fees) and net profit only **DKK 3.2B**, with free cash flow of **−DKK 18.9B** because gross investments (DKK 55.0B) were more than twice operating cash flow (DKK 23.7B). A DKK 60B rights issue and ~DKK 46B of divestment proceeds cut net debt to DKK 19.0B.
## Key numbers
**FY2025 (Annual Report, FACT unless noted)**
- Revenue DKK 73,244M (FY24 71,034; FY23 79,255). By type (note 2.2): generation of power 21,121; sale of power 17,246; heat and steam 3,506; sale of gas 6,344; distribution and transmission 326; O&M and other services 4,655; construction agreements 9,036 (Greater Changhua 4 for partners 4,604; partial divestment of Hornsea 3 offshore transmission asset 3,103); government grants 9,638 (FY24 12,201, fell as subsidy contracts for older assets expired); miscellaneous 1,372. Total revenue from customers 62,234.
- Segments: Offshore revenue 54,797 / EBITDA 16,276; Onshore 2,886 / 4,871; Bioenergy & Other 16,031 / 1,358. Offshore EBITDA breakdown: sites, O&M and PPAs 24,341; construction agreements and divestment gains (2,668); cancellation fees (1,362); other (4,035).
- EBITDA 22,448 (FY24 31,959). Excluding new partnerships (−1,255: Hornsea 3 −4.8B, West of Duddon Sands +2.8B, Badger Wind +0.5B, Eleven Mile and Sparta +0.3B) and cancellation fees (−1,362: Hornsea 4 −2.9B, Ocean Wind 1 reversals +1.3B): 25,065 (+1%), within DKK 24–27B guide; split 78% offshore / 17% onshore / 5% bioenergy & other.
- D&A (10,195); impairments (3,633) — main contributors: updated US tariff assumptions, stop-work and lease-suspension orders on Revolution Wind and Sunrise Wind, US regulatory uncertainty, divestment of European onshore, Hornsea 4 decision; partly offset by lower long-dated US rates. EBIT 8,620 (FY24 6,171). Net financial items (2,881). Profit before tax 5,988; tax (2,823), tax rate 47%. Net profit 3,165 (FY24 16). EPS DKK 2.0. ROCE 5.4% (8.4% adjusted).
- Costs: cost of sales (38,984); employee costs and other external expenses (16,143), of which employee costs (7,080).
- Cash flow: operating 23,741; gross investments (54,976) (offshore 47,724); divestments 12,385; free cash flow (18,850). Net interest-bearing debt 18,978 (FY24 58,027). Rights issue completed 9 Oct 2025, ~DKK 60B gross proceeds. FFO/adjusted net debt 42.9%. Equity 148,941.
- Divestment programme: >DKK 35B target, ~DKK 46B expected proceeds. Hornsea 3: 50% to Apollo, total transaction value ~DKK 39B (agreed 3 Nov, completed 30 Dec 2025); Greater Changhua 2: 55% to Cathay Life / Cathay Power (Dec 2025); European onshore business; West of Duddon Sands 24.5%; two US onshore solar farms 50%; Badger Wind 49%. Brookfield non-controlling owner in four UK farms.
- Revenue by customer location (DKK): GB 35,810; DK 18,000; TW 7,535; DE 5,814; US 3,057; NL 1,713; Other 733; IE 582. No single customer >10% of revenue in 2025 or 2024. Order backlog on construction agreements DKK 37,831M (49% within a year).
- Operations: 35.2 TWh generated (+4%), renewable share 99%; offshore installed capacity 10.2 GW, 8.1 GW under construction (six projects: Greater Changhua 2b and 4, Borkum Riffgrund 3, Hornsea 3, Baltica 2, Sunrise Wind, Revolution Wind); total renewable capacity >18 GW. Employees (FTE) 7,896; ~2,000 positions to be cut by end of 2027. Danish State 50.1%, Equinor 10%.
- US: Revolution Wind stop-work order 22 Aug 2025, preliminary injunction 22 Sep; both Revolution Wind and Sunrise Wind received 90-day suspension orders 22 Dec 2025; injunctions granted 12 Jan and 2 Feb 2026; work resumed.
- Hornsea 4 discontinued in its current form (seabed lease, grid connection, key permits kept). Tonn Nua (900 MW, Ireland, with ESB) awarded Q4 2025. OSONIC low-noise monopile installation (99% noise reduction per Ørsted) to be licensed to third parties.
**H1 2026 (Interim report, FACT, unaudited)**
- Revenue DKK 48,268M (H1 2025 37,840; +28%); EBITDA 14,968 (−4%); excluding new partnerships and cancellation fees 14,980 (+8%; Q2 5,435 vs 5,339). D&A (5,104); impairments (2,537) (US long-dated interest rates, Hornsea 4). EBIT 7,327; profit before tax 5,935; tax (2,627), 44% rate; profit 3,308 (H1 2025 8,238).
- Gross investments 18,261; net interest-bearing debt DKK 22.0B at 30 Jun 2026; FFO/adjusted net debt 44.6%. Offshore generation 11.2 TWh (+23%), availability 91%; offshore + onshore 19.8 TWh.
- Progress: Baltica 2 foundations 103 of 111; Sunrise Wind 77 of 84 foundations, ~50% complete, full commissioning H2 2027; three projects (2.5 GW) expected to be commissioned in H2 2026; European onshore divestment closed April 2026; dividend reinstatement targeted for FY2026 (first payment 2027).
- Guidance 2026 (unchanged 13 Aug): EBITDA ex new partnerships and cancellation fees above DKK 28B (offshore higher, onshore in line, bioenergy & other lower); gross investments DKK 50–55B. These are company outlook, not results.
## What is NOT disclosed (do not invent)
- Contract price levels (CfD strike prices, PPA prices) per project are not summarised on the canvas; only that they are fixed or inflation-indexed for most farms.
- Customer names for PPAs and the split of revenue between CfD-backed and merchant power.
- Euro-denominated revenue or net profit (Ørsted reports in DKK; euro values are conversions).
## Block coverage map
Key Partners: Apollo, Cathay, Brookfield, Danish State, Equinor, Siemens Gamesa and other suppliers, governments and grid operators.
Key Activities: develop, build, operate, farm-down, trade and optimise, OSONIC.
Key Resources: capacity, leases and grid connections, people, balance sheet, know-how.
Value propositions: price-certain clean power, delivery of offshore wind, contracted-cash-flow stakes.
Customer relationships: long contracts, availability, partner co-ownership, regulators, communities.
Channels: auctions and tenders, contracts and PPAs, power exchanges, partner negotiations, B2B.
Customer segments: governments and subsidy schemes, wholesale markets, heat customers, co-investors.
Cost structure: cost of sales, people, D&A, financing, impairments, capex.
Revenue streams: generation, grants, construction agreements, resold power, heat, gas, services; farm-down proceeds as funding.